Rosatom has announced the conclusion of concrete pouring for the turbine plant foundation of Akkuyu nuclear power plant's Unit 2, in Türkyie. This will allow workers to begin the turbine set installation in the unit.
It will take about 30 days for the concrete to reach its desired strength. The quality of the pouring will be checked by a special committee alongside the Nuclear Regulatory Authority (NDK) and an independent inspection entity.
Once all inspections are over, installation of the turbine plant foundation will be considered finished.